Drilling works for project documentation for the construction of the 2nd section of the new traffic connection between the Velenje South Junction and the Slovenj Gradec South Junction - Lot 2
Investment value: cca. 400 mio €
Our role: Carrying out the drilling works for the project's analyses in cooperation with the Geology Department.
Year of the design of technical documentation: 2019-2020
Carrying out field investigations as part of the preparation of the detailed design project documentation and building permit documentation for the construction of the 2nd section of the new traffic connection between the Velenje South Junction and the Slovenj Gradec South Junction - Lot 2.
Our work on the project:
Drilling management and execution of drilling works,
Drilling of geomechanical boreholes, structural boreholes using conventional double tube core barrels and wireline technology to depths of up to 150 m. Carrying out inclinometric, piezometric boreholes and boreholes for seismic analyses.