Geological and geomechanical studies for the construction of a hydroelectric power plant on the Sava River
Investor: HSE d. o. o.
Phase: IDZ
Client: HSE d. o. o.
Design of project documentation: 2009
Project lead: dr. Vladimir Vukadin, engineer of geology
Inv. value: € 300.000.000
Contr. value: € 1.000.000
Project description
Carrying out geological, geomechanical, geophysical, hydrogeological and seismological investigations for the project documentation for the construction of the accumulation and the dam/engine room for: the Suhadol HPP, the Trbovlje HPP and the Ponoviče - Pogonik HPP. Carrying out investigations for the protection of existing infrastructure and facilities.
Carrying out investigations for the protection of drinking water.
Establishment of geotechnical and hydrogeological monitoring.
Technical properties
The hydropower plants will be built in the Sava River canyon in challenging geological and geomorphological conditions. The Ljubljana - Zagreb international railway line and the Ljubljana - Zidani Most main road pass through the planned basins, which will make construction very challenging, as the smooth flow of traffic must be ensured at all times.